Site Progress - April

Further progress has been made on the jetties and boardwalk installations that were under construction last month including the heat pump installation beneath the main jetty.

Internally mechanical and electrical first fix is ongoing throughout the buildings including preparing the main exhibition space and reception area for the underfloor heating system that will be laid soon.

A major milestone has been reached this month with the start of the copper cladding installation on site. The bespoke profiled cladding wrapping the buildings is now being installed on multiple fronts. The timber weather boarding to the boathouse at the centre of the museum is also being installed, enclosing the wet dock ready for boats to be moored inside.